A patio project, planned out

A patio is a project before it is an order: the size, the slab, the joint width and the depth of the build-up all come first, and only then is there a quantity to buy. This page is the route through those decisions, with the take-off the paving calculator returns for the 5 m by 4 m example below.

The plan

This is the patio for sitting on, not a driveway: 100 mm of compacted MOT Type 1 under it, then a 40 mm sharp sand bedding course, then the slabs. The drawing and the take-off below are for one stated example — a 5 m by 4 m patio, 20.0 m², in 600 × 600 mm slabs with 10 mm joints and 10% for the cuts.

Nothing on this page works anything out. Every quantity comes from the same paving engine the paving calculator runs, so if you change a number the calculator is where you change it; this page shows what it returns and what to do with it.

Plan the space first

Four decisions set everything else. Make them before you buy anything, because changing any one of them changes the whole order — and they are the four inputs the paving calculator asks for.

Those four — size, slab, joint width and sub-base depth — are the paving calculator’s own inputs. Enter them there and it returns the slabs, sub-base, bedding sand, jointing and edge restraint in one list you can add to a project.

Open the paving calculator →

Patio project — 5.00 m × 4.00 m A plan drawing of the job, dimensioned, with the figure the calculator returns underneath it. Patio project — 5.00 m × 4.00 m600 × 600 mm slabs, 10 mm joints5.00 m4.00 m20.0 m². Counted on the 600 mm slab + 10 mm joint module63 on the grid, 70 to order with 10% for cuts
20.0 m². Counted on the 600 mm slab + 10 mm joint module

Doing it, in order

  1. Decide the four things above first: size, slab, joint width and sub-base depth. Everything after this is those decisions being built.
  2. Set the patio out with pegs and a line, checking both diagonals are equal so the corners are square, and let it fall away from the house.
  3. Excavate to the depth of the build-up — the sub-base, the bedding and the slab itself — and decide before you start where the spoil is going.
  4. Lay and compact the MOT Type 1 in two layers, watering it as you go if it is dusty, until it is firm underfoot.
  5. Bed the edge restraint on a concrete haunch along the open sides — the sides that meet soil or a step, not the side against the house.
  6. Screed the sharp sand bedding to a consistent 40 mm, lay the slabs on the module, point the joints, then keep people off it for as long as the maker asks.

Don’t forget

Material take-off for this plan

Worked out by the site’s own Paving for this plan’s dimensions, not typed in by hand.

Paving slabs needed70slabs

The working

WorkingValue
Paving area20.0 m² 5.00 m × 4.00 m
Slabs per row9 across × 7 down 600 × 600 mm with 10 mm joints
Slabs before waste63 Plus 10% for cuts and breakages
MOT Type 1 sub-base3.60 t 20.0 m² × 100 mm × 1.8 t/m³
Sharp sand bedding1.28 t 20.0 m² × 40 mm × 1.6 t/m³

What to order

MaterialQuantityNotes
Paving slabs 600 × 600 mm70 slabs9 × 7 = 63 plus 10% for cuts.
MOT Type 1 sub-base3.6 tonnes≈ 5 × 850 kg bulk bags at 100 mm compacted.
Sharp sand (bedding)1.28 tonnes≈ 52 × 25 kg bags, or 2 bulk bags, at 40 mm.
Edge restraint / kerb and concrete haunch18 mRule of thumb: the open perimeter, 18.0 m here. An edge that is not restrained lets the paving spread — a kerb on a concrete haunch, or a proprietary edge, is what holds it. Only the edges that meet soil or a drop need it.
Jointing sand or paving groutestimate onlyestimateCheck the manufacturer's coverage for your joint width.

Sub-base depth is the one number people get wrong. 100 mm compacted is fine for a footpath or light patio; go to 150 mm for anything a car will park on.

A patio project, planned out FAQs

How many slabs do I need for a 5 m by 4 m patio?

70 slabs of 600 × 600 mm with 10 mm joints, from the paving calculator. The grid takes 63 — 9 across by 7 down — and the order is 70 once the 10% cutting allowance is added.

How much sub-base does a 5 m by 4 m patio need?

3.60 tonnes of MOT Type 1 at 100 mm compacted, which is about five 850 kg bulk bags. That is the figure the paving calculator returns for 20.0 m² at that depth.

How much sharp sand goes under the slabs?

1.28 tonnes at a 40 mm bedding depth, which is about 52 bags of 25 kg or two bulk bags. Bedding between 30 mm and 50 mm is the usual range.

Is 100 mm of sub-base enough for a patio?

For a patio you sit on, yes. Go to 150 mm for anything a car will park on — the paving calculator takes the depth as an input, so you can see what the heavier figure costs.

Does this page calculate the patio itself?

No. It hands off to the paving calculator: change the size, the slab, the joint width or the depths there and it returns an updated list you can add to your project.