A small patio, planned out

A 4 m by 3 m patio is about the smallest size that takes a small table and two chairs without feeling tight, and it is a two-weekend job. The plan below is the whole job: what goes under it, what it is laid on, and the quantities the paving calculator returns for exactly these dimensions.

The plan

This is a patio for sitting on, not a driveway: 100 mm of compacted MOT Type 1 under it, then a 40 mm sharp sand bedding course, then the slabs. The paving calculator in the plan below is the same engine the paving calculator page runs, so the take-off is what that page would give you for these numbers.

The layout is a simple running grid, 600 × 600 mm slabs with 10 mm joints. Nothing is cut except the edges, which is why the cutting allowance is 10% rather than more.

Patio plan — 4.00 m × 3.00 m A plan drawing of the job, dimensioned, with the figure the calculator returns underneath it. Patio plan — 4.00 m × 3.00 m600 × 600 mm slabs, 10 mm joints4.00 m3.00 m12.0 m². Slabs across = length ÷ (slab + joint), rounded up35 on the grid, 39 to order with 10% for cuts
12.0 m². Slabs across = length ÷ (slab + joint), rounded up

Doing it, in order

  1. Set out the patio with pegs and a line, checking both diagonals are equal so the corners are square.
  2. Excavate to the depth of the build-up: 100 mm sub-base, 40 mm bedding, plus the slab thickness, and allow for the fall away from the house.
  3. Lay and compact the MOT Type 1 sub-base in two layers, watering it as you go if it is dusty.
  4. Bed the edge restraint on a concrete haunch along the open sides — the sides that meet soil or a drop.
  5. Screed the sharp sand bedding to a consistent 40 mm, then lay the slabs on the module, tapping each one down to the line.
  6. Point the joints with jointing sand or a paving grout, then keep people off it for the time the manufacturer asks for.

Don’t forget

Material take-off for this plan

Worked out by the site’s own Paving for this plan’s dimensions, not typed in by hand.

Paving slabs needed39slabs

The working

WorkingValue
Paving area12.0 m² 4.00 m × 3.00 m
Slabs per row7 across × 5 down 600 × 600 mm with 10 mm joints
Slabs before waste35 Plus 10% for cuts and breakages
MOT Type 1 sub-base2.16 t 12.0 m² × 100 mm × 1.8 t/m³
Sharp sand bedding0.77 t 12.0 m² × 40 mm × 1.6 t/m³

What to order

MaterialQuantityNotes
Paving slabs 600 × 600 mm39 slabs7 × 5 = 35 plus 10% for cuts.
MOT Type 1 sub-base2.16 tonnes≈ 3 × 850 kg bulk bags at 100 mm compacted.
Sharp sand (bedding)0.77 tonnes≈ 31 × 25 kg bags, or 1 bulk bags, at 40 mm.
Edge restraint / kerb and concrete haunch14 mRule of thumb: the open perimeter, 14.0 m here. An edge that is not restrained lets the paving spread — a kerb on a concrete haunch, or a proprietary edge, is what holds it. Only the edges that meet soil or a drop need it.
Jointing sand or paving groutestimate onlyestimateCheck the manufacturer's coverage for your joint width.

Sub-base depth is the one number people get wrong. 100 mm compacted is fine for a footpath or light patio; go to 150 mm for anything a car will park on.

A small patio, planned out FAQs

How many slabs do I need for a 4 m by 3 m patio?

39 slabs of 600 × 600 mm with 10 mm joints, from the paving calculator. The grid takes 35 slabs — 7 across by 5 down — and the order is 39 once a 10% cutting allowance is added.

How much sub-base does a 4 m by 3 m patio need?

2.16 tonnes of MOT Type 1 at 100 mm compacted, which is about three 850 kg bulk bags. The calculator works it out as 12.0 m² × 100 mm × 1.8 tonnes per cubic metre.

How much sharp sand goes under the slabs?

0.77 tonnes at a 40 mm bedding depth, which is about 31 bags of 25 kg or one bulk bag. Bedding depth between 30 mm and 50 mm is the usual range.

Is 100 mm of sub-base enough for a patio?

For a footpath or a light patio, yes. Go to 150 mm for anything a car will park on. The paving calculator takes the depth as an input so you can see what the heavier figure costs.