A shed base, planned out

A shed is only as straight as the base under it. This plan is a 3 m by 2 m concrete base for a typical garden shed: 100 mm of compacted sub-base, then a 100 mm reinforced slab at a 1:2:4 mix. The quantities come from the shed-base calculator for exactly these dimensions.

The plan

The calculator sizes both layers and both ways of getting the concrete: a ready-mix wagon, or bags mixed on site. The bags come straight from the concrete calculator's mix table for a 1:2:4 mix, so the two pages cannot disagree.

It also puts steel mesh and the perimeter joint filler into the take-off, because a slab that size wants both — mesh for the slab itself, and a compressible board where it meets anything it is not bonded to.

Shed base plan — 3.00 m × 2.00 m A plan drawing of the job, dimensioned, with the figure the calculator returns underneath it. Shed base plan — 3.00 m × 2.00 mconcrete slab on compacted sub-base3.00 m2.00 m6.00 m² × 100 mm = 0.600 m³ at a 1:2:4 mix1.19 t MOT Type 1 · 0.63 m³ ready-mix
6.00 m² × 100 mm = 0.600 m³ at a 1:2:4 mix

Doing it, in order

  1. Mark the base out and check the diagonals are equal, then allow a little on each side so the base stands proud of the shed — it is what sheds water away from the frame.
  2. Excavate to the depth of the build-up and compact the bottom of the excavation.
  3. Lay and compact the MOT Type 1 in two layers to a finished 100 mm, checking the level as you go.
  4. Set the mesh on spacers so it sits in the middle of the slab, lapping the sheets and tying the laps with wire.
  5. Stand the expansion board around the perimeter, against anything the slab is not bonded to.
  6. Pour or mix the slab to 100 mm, tamp it level to a slight fall, and cover it while it cures.

Don’t forget

Material take-off for this plan

Worked out by the site’s own Shed base for this plan’s dimensions, not typed in by hand.

Concrete needed0.600 m³wet volume

The working

WorkingValue
Base area6.00 m² 3.00 m × 2.00 m — the shed footprint, with no overhang. A base that runs proud of the shed sheds water away from the frame.
MOT Type 1 sub-base1.19 t 6.00 m² × 100 mm × 1.80 t/m³ compacted, plus 10%. That 1.8 t/m³ is the same figure the gravel and paving calculators quote. ≈ 2 × 850 kg bulk bags.
Concrete slab0.600 m³ 3.00 m × 2.00 m × 100 mm, mix 1:2:4 — from the concrete calculator’s own mix table.
Ready-mix to order0.63 m³ ≈ 1.51 tonnes. Includes the 5% over-order the concrete calculator adds — short loads are costly.
Or mix on site8 cement + 17 sand + 32 agg 25 kg bags, straight from the concrete calculator’s figures for this mix.

What to order

MaterialQuantityNotes
MOT Type 1 sub-base1.19 tonnes≈ 2 × 850 kg bulk bags at 100 mm compacted. Weighted at 1.8 t/m³ — the figure the gravel and paving calculators use.
Ready-mix concrete0.63 m³One line if you are ordering a wagon. The mix comes from the concrete calculator’s own table.
Cement (25 kg bags)8 bagsFor mixing on site — the concrete calculator’s own bag figure.
Sharp sand (25 kg bags)17 bags≈ 422 kg.
Ballast / 20 mm aggregate (25 kg bags)32 bags≈ 792 kg, or 1 bulk bags.
Steel reinforcement mesh A142 (4.8 × 2.4 m sheet)1 sheetRule of thumb: a 4.8 × 2.4 m sheet covers about 11.5 m², and the sheets lap one full square, so 1.12× the area is ordered. A shed base is often laid as a plain slab with no mesh at all. Put mesh in only where the slab is designed to carry it, and take advice if the shed is heavy or the ground is soft.
Mesh spacers / chairs12 spacersRule of thumb: 2 per m² to hold the mesh in the middle of the slab. Mesh lying on the ground or on the membrane reinforces nothing — it has to sit in the concrete.
Tying wire (1.6 mm coil)1 kgRule of thumb: about 1 kg per 20 m² of mesh, to tie the laps. Soft annealed tying wire, not a heavier gauge.
Expansion / perimeter joint filler board10 mRule of thumb: the slab perimeter, 10.0 m here, standing against walls, kerbs, a manhole or an existing slab. A slab pinned all the way round cracks somewhere else instead.

A shed base is not a structural design, and this page does not check the ground, the drainage or the load. A small shed on firm, level, well-drained ground is one thing; a large shed, a workshop, a log store, a hot tub or anything heavy needs a base designed for the load and the ground it sits on — take advice from a competent person. 100 mm of concrete is a typical light-shed slab; a heavier load or softer ground needs more, and the concrete should be laid over a compacted sub-base, not straight onto soil.

A shed base, planned out FAQs

How much concrete do I need for a 3 m by 2 m shed base?

0.600 m³ of wet volume at 100 mm thick, from the shed-base calculator. Ordered as ready-mix that becomes 0.63 m³, because the calculator adds the 5% over-order the concrete calculator uses — short loads are expensive.

Do I need a sub-base under a shed base?

This plan uses 100 mm of compacted MOT Type 1, which comes to 1.19 tonnes for a 6 m² base with a 10% allowance — about two 850 kg bulk bags. It is what turns soft ground into something the slab can sit on.

How many bags of cement, sand and aggregate is that?

For a 1:2:4 mix the calculator returns 8 bags of cement, 17 of sharp sand and 32 of 20 mm aggregate, all 25 kg bags. That is the same mix table the concrete calculator uses.

Do I need reinforcement mesh in a shed base?

This plan includes one A142 sheet on spacers, plus tying wire for the laps. A 4.8 × 2.4 m sheet covers about 11.5 m² and the sheets lap one square, so serving a 6 m² base leaves an offcut.